North Creek Drive Pavement Preservation Project

Roadway Maintenance 

This roadway has been selected by the City of Mill Creek Pavement Preservation Program to receive a pavement overlay.
This work will be phased over the course of 4 months:

  • First Phase: Curb ramp reconstruction. 
  • Second Phase: Removal the top layer of the asphalt (milling) and asphalt patching. 
  • Third Phase: Paving of a new top layer of asphalt on the roadway.
  • Fourth Phase: Adjusting utility castings in the roadway and pavement marking.
Project Start

June 2026

Estimated Project Completion

October 2026

Key Details

  • During construction, North Creek Drive will be local access only. One lane will remain open to traffic for the majority of the construction.
  • During the planning and overlay work there will be a full road closure between driveway access points, with a detour through the development (see N Creek Drive Temporary Detour Map). 
  • Sidewalk access will remain open. However, there will be pedestrian detours. 
  • The overlay process uses hot material that can damage vehicles, clothing, and may stick to your pet's paws. Please obey the traffic signs and flagging personnel.
     

Local Access and Parking

  • No Parking signs will be placed at least 72 hours in advance of construction.
  • Please remove all on street parking before 7 am as noted on these signs to avoid towing. 
  • During the preparatory phases of work, access will remain open and will be facilitated by the flagging personnel. Please respect and obey their directions for both your safety and the crew's.
  • While new asphalt is being placed, there may be delays of up to 30 minutes to enter/exit properties within the project work zone in order to compact the asphalt material and make it safe to drive on. Please plan accordingly.
     