Roadway Maintenance
This roadway has been selected by the City of Mill Creek Pavement Preservation Program to receive a pavement overlay.
This work will be phased and will occur over the course of 4 months:
- Pre-project: The City will replace and repair catch basins.
- First Phase: Curb ramp reconstruction.
- Second Phase: Removal of the top layer of the asphalt (milling) and asphalt patching.
- Third Phase: Paving a new top layer of asphalt on the roadway.
- Post-project: Silverlake Water and Sewer District will replace iron castings in the pavement.
Project Start
June 2026
Work Begins
Jul 27, 2026
Roadway Reconstruction Begins
Aug 17, 2026
Project Completion
October 2026