Roadway Maintenance
This roadway has been selected by the City of Mill Creek Pavement Preservation Program to receive a pavement overlay.
This work will be phased over the course of 4 months:
- First Phase: Curb ramp reconstruction.
- Second Phase: Removal the top layer of the asphalt (milling) and asphalt patching.
- Third Phase: Paving of a new top layer of asphalt on the roadway.
- Fourth Phase: Adjusting utility castings in the roadway and pavement marking.
Project Start
June 2026
Estimated Project Completion
October 2026