In addition, this project is in cooperation with the Silver Lake Water and Sewer District (SLWSD), who will replace the existing water main and install a new sewer main within the same project area. Close coordination with SLWSD is required to ensure seamless integration of the utility upgrades with the street improvements, enhancing transportation infrastructure and overall community functionality.
Missed the Open House?
Fill out the form below to leave feedback or further questions about the project.
Project Timeline
Select Design Consultant
Complete
Jul 14, 2025
City Council Approval of Conceptual Design
Complete
Mar 10, 2026
Apply for WSDOT Grants
Complete
Apr 15, 2026
Finalize 30% Design
In Progress
Amend Design Contract to increase scope from 30% to 100% design
In Progress
Silver Lake Water Sewer District Completes their portion of the project
Pending
Secure Construction Grant Funding
Pending
Advertise for Bid to solicit contractor proposals
Pending
Select Contractor through competitive bid process
Pending
Begin Construction upon contract award
Pending
Project Completion following construction close out
Pending