Project Elements
The project will replace a damaged 36‑inch corrugated metal stormwater pipe running north–south beneath the Sweetwater Ranch neighborhood, perpendicular to 144th Street SE.
Key elements include:
- Installing approximately 444 feet of new 36‑inch plastic stormwater pipe, shifted slightly west of the existing alignment to avoid steep slopes, nearby property lines, existing utilities, and sensitive wetland areas.
- Constructing four new concrete catch basins to support improved stormwater conveyance.
- Using conventional cut‑and‑cover trenching methods for pipe installation.
- Fully abandoning the existing deteriorated stormwater main by filling it with flowable grout to stabilize the pipe and surrounding soils.
- Maintaining neighborhood access and minimizing construction impacts wherever possible.
Pre-Deisgn
Complete
Aug 1, 2024
Design
Complete
Mar 9, 2026
Project Out For Bids
Complete
Apr 28, 2026
Construction
In Progress
Construction begins July 17, 2026