Project Overview
The Silver Crest Park Rehabilitation Project was completed in February 2025, improving the playground, basketball court, pathways, picnic areas, and accessibility. The project was funded through a combination of City funds, a Snohomish County Parks grant, and a Washington State capital appropriation grant. A ribbon-cutting ceremony was held on February 12, 2025, to celebrate the park improvements and reopening to the community.
Park History & Ammenities
The Silver Crest Park was annexed to the City in 2005 as a part of the Northeast Area Annexation. This .61 acre neighborhood park is located within the Silver Crest subdivision on 28th Drive SE. Amenities include a full basketball court, playground, picnic tables, and a grassy play area. There is currently no irrigation in place at this park.
Project Funding
This project is funded through a combination of City funds, a Snohomish County Parks grant, and a State of Washington Capital Appropriation legislative grant.
Project Milestones
The project went to bid for the second time on March 7, 2024, and was awarded to K-A General Construction Contractor L.L.C. The start date for construction was August 2nd, 2024.
The Silver Crest Park project is complete and the park is now open.